Engineer Al Mirza: We Are Continuing To Implement The Jadidah Al-Shat Water Project In Diyala Governorate, And We Will Soon Celebrate The Completion Of The Al-Baghdadi Water Project In Anbar Governorate

Engineer Imad Tawfiq Al Mirza, General Manager of Al-Fao General Engineering Company, stated that our company’s staffs in Diyala Governorate continue to work on the Jadidah Al-Shat water project, which it is implementing for the benefit of the General Directorate of Water.

The Director General stated that the completion rate in the project is (37 %) and its production capacity is (2000) cubic meters / hour. It supplies the Jdeidet Al-Shatt district and the surrounding villages with drinking water, and the work is progressing at an increasing pace and in accordance with contractual timings and international specifications and with Iraqi hands.

On the other hand, His lordship stated that the company completed the Dujail Water Project with a capacity of (4000) cubic meters / hour in Salah al-Din Governorate and is soon preparing to celebrate the opening of the Al-Baghdadi Water Project with a capacity of (3000) cubic meters / hour in Anbar Governorate.

Hot Posts

FIELD VISITS

Recommended Posts