Mr. General Manager: Our company Uses The Latest Technologies In The Implementation Of Water Projects

Engineer Imad Tawfiq Al Mirza, General Manager of Al-Fao General Engineering Company, confirmed the continuation of work on the Jdeidet Shatt Water Project in Diyala Governorate for the General Directorate of Water.

 

His Lordship explained the following:

• The company uses the latest technologies in the implementation of water projects.

• Current works are (installing filter pumps, backwashing system, installing generators, skimmers and hammers).

• Actual completion rate (72%).

• The production capacity of the project is (2000) cubic meters / hour.

• The project supplies the Jdeidet Shatt district and the surrounding villages with potable water.