Successive Engineering Achievements: Al-Fao Continues The Water Sector Reconstruction Revolution In The Provinces
Eng. Ya'rub Qahtan Al-Awad, General Manager of Al-Fao General Engineering Company, confirmed the continuation of work on the Hasiba Al-Sharqiya Central Water Project in Anbar Governorate, which the company is implementing for the General Directorate of Water, affiliated with the Ministry of Construction, Housing, and Municipalities.
🔵 Project Details:
🔹 Ongoing Work:
- Completion of pouring the walls of the silt basin and the underground reservoir.
- Construction of the high-pressure pumping station and pouring the roof of the workshop building.
- Formwork and reinforcement work for the chemical building.
- Steel formwork, detailing, and reinforcement connection for the sedimentation and rapid mixing basins.
🔹Production Capacity:
(2,000) cubic meters/hour.
🔹 Beneficiary Areas:
Eastern Anbar.
🔵 Project Components:
🔹 Treatment Plant:
- Three sedimentation basins.
- Ten filter buildings.
- Ground reservoir.
- Chemical, high-pressure, power, and workshop buildings.
- Sludge basins.
- Two operator quarters.
🔹 Pumping Station:
- Low-pressure and power building.
- Four transmission lines, (25) km in length.
🔵 Other Al-Fao Projects:
🔹 Ongoing Projects:
- Jdeidet Al-Shatt Water (Diyala Governorate): (2,000) cubic meters per hour.
- Balad Water (Salah al-Din Governorate): (4,000) cubic meters per hour.
🔹 Completed Projects:
- Kirkuk Water (Kirkuk Governorate): (12,000) cubic meters per hour.
- Tal Afar Zummar Water (Nineveh Governorate): (10,000) cubic meters per hour.
- Dujail Water (Salah ad-Din Governorate): (4,000) cubic meters per hour.
- Al-Baghdadi Water (Anbar Governorate): (3,000) cubic meters per hour.