Company General Manager: The State Real Estate Building Project In Dhi Qar Governorate Is In The Final Stages Of Completion

Engineer Imad Tawfiq Al Mirza, General Manager of Al-Fao Engineering Company, stated that the staffs of our company in Dhi Qar Governorate continue to work on the state real estate building project in the governorate, which the company is implementing for the Public Buildings Department of the Ministry of Construction, Housing, Municipalities and Public Works.

He stated that the company is proceeding with the completion of this project according to the specified timings and required specifications. The building consists of two floors and includes halls, rooms, and sanitary groups, in addition to systems (internet, fire extinguishing, and cameras).

The General Manager stated that the current work includes (painting the interior walls, installing wooden doors, pouring the site floor and external roofing work) and that the completion rate is (87%).