Director General Of Al-Fao General Engineering Company: Advanced Completion Rates In The Planning Buildings Project In Nineveh Governorate

Engineer Ya'rab Qahtan Al-Awad, Director General of Al-Fao General Engineering Company, a division of the Ministry of Construction, Housing, and Public Municipalities, stated that the company is continuing work on the Planning Buildings Project in Nineveh Governorate, which the company is implementing for the Ministry of Planning.

 

The Director General explained that the project includes several different buildings and halls, and that current work includes:

1) The wooden formwork for casting the two information buildings.

2) Pipe laying.

3) Subflooring, doors, and windows.

4) Curbstone.

 

The current completion rate is (82%), and work is progressing according to the specified timelines and required technical specifications.