Engineer Ya'rab Qahtan Al-Awad, General Manager of Al-Fao General Engineering Company, announced the continuation of work on the Eastern Husaybah Central Water Project in Anbar Governorate. This project is being implemented for the General Directorate of Water and aims to provide potable water to the residents of eastern Anbar.

 

Project Details:

🟣 Production Capacity: (2,000) cubic meters per hour

 

Project Components:

🟣 Main Site (Treatment Plant): Three sedimentation tanks, ten filter buildings, ground tank, chemical buildings, high-pressure and power buildings, workshop, and mud buildings, and two operators' quarters.

🟣 Suction Station Site: Low-pressure building, power, and three transmission lines.

 

Current Work:

🟣 Replacement of soil under the foundations of the project facilities, treated with cement, spraying, and tamping.

🟣 Laying of concrete layers.

🟣 Brick construction work for the outer fence.

 

Project Importance:

🟣 Providing potable water to residents of eastern Anbar.

🟣 Strengthening the water infrastructure in the governorate.

🟣 Improving the level of services provided to citizens.