Company General Manager: The Drop That Waters Hope: Al-Fao Company Realizes the Dream of Eastern Hasiba Water in Anbar

Engineer Ya'rab Qahtan Al-Awad, General Manager of Al-Fao General Engineering Company, confirmed the continuation of work on the Central Eastern Hasiba Water Project in Anbar Governorate, which the company is implementing for the General Directorate of Water.

 

🟢 Project Details:

Production Capacity: (2,000) cubic meters per hour.

Beneficiary Areas: The project serves the residents of eastern Anbar.

 

🟢 Project Components:

Treatment Plant: Includes three sedimentation tanks, ten filter buildings, a ground tank, chemical buildings, high-pressure and power plants, a workshop, slurry tanks, and two operators' quarters.

Intake Station: Includes a low-pressure and power plant building, along with three transmission lines.

 

🟢 Current Work:

Detailing And Connecting The Reinforcing Steel: for the foundation of the underground tank, filter building, and collection basin.

Installing The Steel Formwork: for the foundation of the underground tank and filter building.

Brick Construction Work: for the workshop and engineer's offices.

Pipe Preparation: Pipe preparation work is ongoing.

 

The Director General added that this project reflects Al-Fao General Engineering Company's commitment to providing potable water to the people of eastern Anbar and improving the level of services in the governorate.