Within The Service And Engineering Effort Projects: Work Continues On The Project To Develop The Fifth Police District And Shuhada Al-Saydiyah In Baghdad Governorate.
Engineer Imad Tawfiq Al Mirza, General Manager of Al-Fao General Engineering Company, stated that the staff of our company continues to work day and night on the project to develop sectors (833, 867 and 869) in the Fifth Police District and Shuhada Al-Saydiya within the Al-Rashid municipality sector in Baghdad Governorate.
The Director General stated that the project work includes:
1) Earthen excavations, burial with crushed gravel, and covering with asphalt.
2) Extending and connecting the heavy water network and the pure water network to residential homes.
3) Extending and connecting the heavy water pipeline network of the conveyor line (1300) meters long to the main outlet.
4) Extending and connecting the pure water pipeline network of the transmission line with a length of (2100) meters to the main outlet.
5) Connecting heavy water connections to residential homes with the conveyor line.
His Lordship explained that the current work is (pouring floors under the roads to process rattan). Asphalt (paving) work for sector (867) will soon begin, noting that the staff will be strengthened in order to reduce the time period and speed up completion in order to serve the people of these areas.