1 |
Al- Roumaitha Bridge |
2004 |
AL-Muthanna |
252.174.000 |
2 |
Reconstruction Of The Company Head Office |
2004 |
Baghdad |
788.414.157 |
3 |
Rehabilitation Of The Ministry Stores In Alamiryah |
2005 |
Baghdad |
174.468.042 |
4 |
Talafar Water Station – Unified Zummar (1st Stage) |
2005 |
Nineveh |
6.066.351.000 |
5 |
Water Injection – West Of Qurna (4th Stage) |
2005 |
AL-Basra |
827.751.240 |
6 |
Rehabilitation Of Baghdad Touristic Island |
2005 |
Baghdad |
767.375.000 |
7 |
The Building Of The Administration Of Babil Sewerage Network |
2006 |
Babil |
461.841.620 |
8 |
The Second Passage Bridges To AL-Khalis-AL-Adhaim Highway |
2006 |
Diyala |
1.479.823.668 |
9 |
Petroleum Products Building |
2007 |
Maysan |
805.500.000 |
10 |
Design Drawings For Ibn-Albaladi Hospital |
2007 |
Baghdad |
102.900.000 |
11 |
Consultations To Al-Najaf Hospital |
2007 |
Holy Najaf |
200.000.000 |
12 |
Water Pipe Line Of Ain - AL-Tamer Province |
2007 |
Sacred Karbala |
1.351.600.000 |
13 |
Manufacturing Of Caravans |
2007 |
Baghdad |
61.600.000 |
14 |
Schools Building |
2008 |
All Governorates |
47.428.945.070 |
15 |
Head Office Building For The General Commission For Taxes |
2008 |
Al-Diwaniyah |
722.154.332 |
16 |
Traffic Control Buildings |
2008 |
Babil |
1.611.925.746 |
17 |
AL Sarrafya Truss Bridge Reconstruction |
2008 |
Baghdad |
13.000.000.000 |
18 |
Rehabilitation Of Measurement And Quality Control Laboratories |
2008 |
Baghdad |
145.889.000 |
19 |
Rehabilitation Of Measurement And Quality Control Service Building |
2008 |
Baghdad |
115.443.315 |
20 |
The Installation Of First Floor In The Training Building |
2008 |
Baghdad |
453.550.000 |
21 |
Rehabilitation Of Arar Buildings Complex Border Outlet |
2008 |
AL-Anbar + Sacred Karbala |
4.110.394.661 |
22 |
Hilla Gas Turbine Power Station Building |
2008 |
Babil |
4.364.150.500 |
23 |
Ministry Of Construction & Housing \ Head Office Building |
2008 |
Holy Najaf |
2.954.111.503 |
24 |
Grains Silo Expansion |
2008 |
AL-Anbar |
4.416.154.293 |
25 |
Electric Power Transmission Administration Building |
2008 |
Baghdad |
2.313.838.000 |
26 |
Improvement Of Crude Oil Discharging site |
2008 |
Baghdad |
831.762.500 |
27 |
Improvement Of The Main Road In Hindiya |
2009 |
Babil |
1.408.866.400 |
28 |
The Maintenance Of Chalt , AL-Teeb , Border Line |
2009 |
Maysan |
1.872.025.000 |
29 |
Execution Of Exterior Pipe Line With Capacity (70.000) Burrels In AL-Doora Refinery |
2009 |
Baghdad |
4.674.855.000 |
30 |
Treatment Of The Third Chimney In AL-Doora Electrical Power Station |
2009 |
Baghdad |
350.000.000 |
31 |
Treatment Of The Fourth Chimney In AL-Doora Electrical Power Station |
2009 |
Baghdad |
300.000.000 |
32 |
The Work Includes Installing Electrical Elevator And The Treatment Of The Third Chimney From Level (20m Up To 100m) In AL-Doora Electrical Power Station |
2009 |
Baghdad |
375.000.000 |
33 |
The Execution Of Weight Bridge With (75) Ton Capacity In Beejy |
2009 |
Salah AL-Din |
98.963.600 |
34 |
The Laying Of Cooling Tube (16) Inch In AL-Doora Refinery |
2009 |
Baghdad |
117.698.000 |
35 |
Execution The Residual Work In Scholastic Buildings |
2009 |
AL-Anbar + AL-Diwania |
3.438.075.072 |
36 |
Replacing The Re-Heat Coils For The Fourth Chimney In AL-Doora Electrical Power Station |
2009 |
Baghdad |
850.000.000 |
37 |
Executing A Third Floor For The Civilian Defense General Head Quarters |
2009 |
Baghdad |
1.385.979.000 |
38 |
Talafar Water Station – Unified Zummar (2st Stage) |
2009 |
Nineveh |
45.203.116.555 |
39 |
Supplying The Imported Equipments For The Project Of Tellafor - Zummar Unified - Second Stage |
2009 |
Nineveh |
22.634.195.136 |
40 |
Digging And Reclamation Company - AL-Burjisiya |
2009 |
AL-Basra |
1.885.779.000 |
41 |
Improvement Of Al_Hindiya City Nearby Babylon Governorate |
2009 |
Babil |
3.972.232.000 |
42 |
Installation Of The South Head Quarter Building - AL-Burjisiya |
2009 |
AL-Basra |
2.648.690.000 |
43 |
Installation Of AL-Fao Oil Storage Building |
2009 |
AL-Basra |
1.657.610.600 |
44 |
Beji Refineries Company Gates |
2009 |
Salah AL-Din |
937.605.000 |
45 |
Execution The Capacity Of Storage In AL-Risafa Gas Factory |
2010 |
Baghdad |
658.710.762 |
46 |
Execution Of Concrete Baes For AL-Kufa Cement Factory |
2010 |
Holy Najaf |
3.211.628.056 |
47 |
The Execution Of Infrastructure For Thee-Qar University (2 th Stage) |
2010 |
Dhi-Qar |
3.212.591.000 |
48 |
The Civil And Mechanical Works For The Pipes Of Second Refinery Unit In AL-Dora |
2010 |
Baghdad |
3.023.763.500 |
49 |
The Civil And Mechanical Works For The Cooling Pipes Of Second Refinery Unit In AL-Dora |
2010 |
Baghdad |
1.630.067.000 |
50 |
Measurement And Quality Control |
2010 |
Baghdad |
3.336.217.500 |
51 |
Execution The Residual Work In Scholastic Buildings |
2010 |
Maysan |
5.330.499.330 |
52 |
The Treatment Of The Settlement Of AL-Clinker Conveyor For The First Line Of Kerbalaa Cement Factory |
2010 |
Sacred Karbala |
96.912.000 |
53 |
Execution of closed sport hall (500) audiences [Al- gadwal al-gharbi , al-hussainiya , al-mahaweel , al-hendiya] |
2010 |
Sacred Karbala + Babil |
6.241.187.500 |
54 |
Execution Of The Third Stage Of AL-Bergisiyah Head Quarters |
2010 |
AL-Basra |
2.377.910.000 |
55 |
Install The Steam Boiler In Kirkuk Refinery |
2010 |
Kirkuk |
597.550.000 |
56 |
Execution Of Sewage Network In AL-Naft-District / Beiji |
2010 |
Salah AL-Din |
648.730.000 |
57 |
Execution The Fence For AL-Nasiriyah Gas Factory |
2010 |
Dhi-Qar |
251.140.000 |
58 |
Execution Of Boilers Foundations Of Salah AL-Din (2 th Stage) Refinery |
2010 |
Salah AL-Din |
439.050.000 |
59 |
Execution Of Works Under D. P. C. For The Building Of The Internet Company |
2010 |
Salah AL-Din |
204.817.000 |
60 |
Execution First Floor In The Steel Shades In The Mechanical Workshop |
2010 |
AL-Basra |
450.000.000 |
61 |
Transport And Install Water Tank For Fire Equipments |
2010 |
Baghdad |
40.500.000 |
62 |
Treatment of the sixth chimney unit in AL-Dora electric station |
2011 |
Baghdad |
1.000.000.000 |
63 |
Housing Units In Hai-Al Jhad |
2011 |
Baghdad |
19.248.000.117 |
64 |
Manufacturing And Erecting Steel Shodes Of AL-Kafa Cement Factory |
2011 |
Holy Najaf |
4.300.000.000 |
65 |
Execution Of Football Stadium For Housing Units Of AL-Dora Refinery |
2011 |
Baghdad |
394.270.000 |
66 |
Construction Of The Educational Oil Tower Base / AL-Burjisiya / 9 |
2011 |
AL-Basra |
236.856.000 |
67 |
AL-Sheah-Wakf- Housing Complex |
2011 |
Holy Najaf |
3.858.772.000 |
68 |
Execution AL-Naisr Exchange For Communication |
2011 |
Al-Diwaniyah |
438.162.500 |
69 |
Execution Of The Second Stage Of AL-Bergisiyah Water Storage And The Fence |
2011 |
AL-Basra |
1.100.167.000 |
70 |
The Civil Works For (RO) Unit In Middle Refinery Company |
2011 |
Baghdad |
910.294.500 |
71 |
Design And Execution Closed Store In Beiji |
2011 |
Salah AL-Din |
878.000.000 |
72 |
Concrete Works For Salah Al-Din Refinery Steam Boilers / Baigy 1 |
2011 |
Salah AL-Din |
747.660.000 |
73 |
Renovation OF Inspection Sector Building In The Gas Filling Company |
2011 |
Baghdad |
105.531.000 |
74 |
Execution Of The Security Fence For The Northern Refinery Company In Beiji |
2011 |
Salah AL-Din |
3.835.000.000 |
75 |
Housing Complex In Al-Sayada |
2011 |
Kirkuk |
49.824.240.886 |
76 |
Sabeaa Temple |
2011 |
Dhi-Qar |
889.114.000 |
77 |
Construction Of The Man Entrance Road Of The Iraqi Drilling Company Building / AL-Burjisiya/ 8 |
2011 |
AL-Basra |
360.450.000 |
78 |
Restudy, Design, Preparing Of Drawings And Bill Of Quantities For The Completion Works Of AL-Qadisiah Water Project |
2011 |
Salah AL-Din |
60.000.000 |
79 |
Construction Of Cooling Water Pipe For Fuel Improvement Unit And LPG Unit In AL-Dora Refinery |
2011 |
Baghdad |
162.395.000 |
80 |
Installation Of Pipes Net Work For Gas Generator In AL-Dora Refinery |
2011 |
Baghdad |
594.177.000 |
81 |
Execution The Building Of Police Station In AL-Dora |
2011 |
Baghdad |
3.111.852.100 |
82 |
Execution Of The Materials Management Building Of The Gas Filling Company |
2011 |
Baghdad |
291.703.000 |
83 |
Execution Of Pipes Network For The Gas Generator In Al-Dora Refinery |
2011 |
Baghdad |
636.871.800 |
84 |
Execution Of Reservoirs Paining Works For The Middle Refinery Company |
2011 |
Baghdad |
236.810.000 |
85 |
Execution Of Reservoirs Bases For The Northern Gas Company |
2011 |
Kirkuk |
103.960.000 |
86 |
Rehabilitation Of Iskan Sport Club |
2011 |
Baghdad |
283.248.500 |
87 |
Installation Of Quests Home In -AL-Bergisiyah (Stage One) |
2011 |
AL-Basra |
1.798.275.000 |
88 |
Water Injection – West Of Qurna (4 ، 5 ، 6) |
2011 |
AL-Basra |
1.200.267.919 |
89 |
Water Pump Installation At The Tigris Bank In Al-Dora Refinery |
2011 |
Baghdad |
486.549.800 |
90 |
Implementation Of (BRC) Fence For Fuel Improvement Unit In Al-Dora Refinery |
2011 |
Baghdad |
13.300.000 |
91 |
Spheris Storage In AL-Gas Company |
2011 |
Baghdad ، Babil ، AL-Diwania ، AL-Basra ، Maysan ، Dhi-Qar ، Wasit ، Holy Najaf ، Nineveh |
13.788.138.680 |
92 |
Treatment of the fifth chimney unit in AL-Dora electric station |
2011 |
Baghdad |
1.000.000.000 |
93 |
Connecting ( Ø 8") Fire Fighting Water Pipe From Al-Dora Refinery To Gas Plant |
2011 |
Baghdad |
104.305.000 |
94 |
Reconstruction & Rehabilitation Of Wasitt Governorate Building |
2011 |
Wasit |
2.124.827.500 |
95 |
Execution Of AL-Bathaa Markets |
2011 |
Dhi-Qar |
1.269.688.000 |
96 |
Connecting Electricity From Zoss Station In Zubair To The New South Operation Division And The Housing Complex / AL-Burjisiya / 6 |
2011 |
AL-Basra |
3.142.064.000 |
97 |
Execution Of The Sand Works For The Modern Complex Of Food Stuffs Supply |
2011 |
Arbil |
1.047.200.000 |
98 |
Execution Of Site Laboratory Building And The Central Meeting Room In Al-Dora Refinery |
2011 |
Baghdad |
658.140.000 |
99 |
Execution Of Civil Works For The New Boiler In Oil Northern Refineries |
2012 |
Baghdad |
2.202.348.500 |
100 |
Execution Of Booster Pumps Foundations For AL-Fao Oil Storing |
2012 |
AL-Basra |
1.109.460.000 |
101 |
Water Pipe Works For Sector (18) In Al-Dora Refinery |
2012 |
Baghdad |
631.900.000 |
102 |
Execution Of The College Of Sciences / Diyala University |
2012 |
Diyala |
1.995.741.700 |
103 |
Construction Of Administration Building For AL-Furat Chemical Industries Company |
2012 |
Sacred Karbala |
471.780.000 |
104 |
Execution Building of Boarding Houses For Oil Training Institute |
2012 |
AL-Basra |
5.688.279.000 |
105 |
Construction Of Iraqi Drilling Company Building / AL-Burjisiya /7 |
2012 |
AL-Basra |
7.568.502.250 |
106 |
Administration Building Works In AL-Moftyah Gas Plant |
2012 |
AL-Basra |
100.000.000 |
107 |
The Construction Of Visitors City In AL-Hindiya |
2012 |
Sacred Karbala |
754.841.181 |
108 |
Housing Complex In Al-Salam |
2012 |
Holy Najaf |
49.357.456.200 |
109 |
Foundation Works For Internet Building // SCIS |
2012 |
Holy Najaf |
315.769.500 |
110 |
Road Works In Ninevah Gaseous Power Station |
2012 |
Nineveh |
1.561.000.000 |
111 |
Control Rooms Maintenance In Al-Dora Refinery |
2012 |
Baghdad |
450.738.000 |
112 |
Execution Of The Final Stages For The College Of Education / Sacred Karbalaa University |
2012 |
Sacred Karbala |
3.601.942.500 |
113 |
Cars Repairing Workshop / First Stage |
2012 |
Baghdad |
1.071.344.000 |
114 |
Industrial Sheds Works In Cylinders Repairing Factory At Hammam AL-Alyl |
2012 |
Nineveh |
1.948.504.000 |
115 |
Filter Pipe Works For Sector (7 / 4) In Al-Dora Refinery |
2012 |
Baghdad |
1.208.625.000 |
116 |
Earth Works In AL-Mansoryah Gas Power Station |
2012 |
Diyala |
9.238.138.500 |
117 |
Industrial Sheds Works In Cylinders Repairing Factory At Hammam AL-Alyl / (4th Stage) |
2012 |
Nineveh |
1.962.963.000 |
118 |
Continuation Works For The Steam Boiler And The Steel Structure For The Middle Refinery Company In Al-Dora Refinery |
2012 |
Baghdad |
467.841.250 |
119 |
Execution Of Administration Building For AL-Taji Electrical Gas Station No. (2) |
2012 |
Baghdad |
374.820.000 |
120 |
Road Works In AL-Mansoryah Gas Power Station |
2012 |
Diyala |
2.000.000.000 |
121 |
Rehabitation Of Stores And Service Rooms In AL-Kout Machinery Workshop |
2012 |
Wasit |
253.925.000 |
122 |
Foundation Works For Internet Building // SCIS |
2012 |
Babil |
328.570.500 |
123 |
Water Intake Works In AL-Diwaniyah Gaseous Power Station |
2012 |
Al-Diwaniyah |
2.827.475.000 |
124 |
Fixing The Coating Of The Fifth Chimney For Electrical Heating Station In Al-Dora |
2012 |
Baghdad |
950.000.000 |
125 |
Soda Tanks Works Of (4) In Chemical Industries Company |
2012 |
Sacred Karbala |
441.863.500 |
126 |
Execution Of Building At The State Company For Internet Services // SCIS |
2012 |
Dhi-Qar |
608.168.500 |
127 |
Civil Works For Cylinders Repairing Works shop In AL-Nasiryah / 4 |
2012 |
Dhi-Qar |
1.986.983.000 |
128 |
Civil Works Of Concrete Sleeves And Steel Structure For The Feeding Pipes Of Azmara Unit |
2012 |
Baghdad |
1.993.008.000 |
129 |
Supplying , installing And Operating Of Water Treatment Unit In AL-Gayarah Refinery |
2012 |
Nineveh |
830.000.000 |
130 |
Sanitary Works Network In Al-Dora Refinery |
2012 |
Baghdad |
2.267.825.000 |
131 |
Road Works In AKAZ Gaseous Power Station |
2012 |
AL-Anbar |
5.260.387.800 |
132 |
Civil Works For Cylinders Repairing Works shop In AL-Nasiryah / 2 |
2012 |
Dhi-Qar |
1.988.707.000 |
133 |
Execution Of Fence Surrounding Globular Tank In AL-Ramady Gas Foundry \ Gas Filling Company |
2013 |
AL-Anbar |
702.270.000 |
134 |
Rehabilitation Of Sayedet AL-Najat Church With An Extension Of The Contract No. (1) |
2013 |
Baghdad |
2.860.194.500 |
135 |
(OSEL) Pipes Works For Azmara Unite |
2013 |
Baghdad |
1.565.017.500 |
136 |
Execution And Renew Of Fire Fighting Pipes Network In Al-Dora Refinery / 2nd Stage |
2013 |
Baghdad |
3.125.796.500 |
137 |
Construction Of Mechanicals Building At Production Department In Gas Filling Company |
2013 |
Baghdad |
160.371.000 |
138 |
Water Intake For AL-Kairat Gaseous Power Station |
2013 |
Sacred Karbala |
1.770.000.000 |
139 |
Water Intake For AL-Haidaryh Gaseous Power Station |
2013 |
Sacred Karbala |
4.712.000.000 |
140 |
Earth Filling Of Floor In Middle Euphrates Gas Store |
2013 |
Babil |
453.700.000 |
141 |
Ministry Of Construction & Housing \ Head Office Building |
2013 |
AL-Muthanna |
3.525.545.120 |
142 |
Supply Pipes Network For The New Dura Workhouse In Al-Dora Refinery |
2013 |
Baghdad |
832.766.175 |
143 |
Execution Of Second Floor Laboratory Building Of The Middle Refinery Company |
2013 |
Baghdad |
244.495.000 |
144 |
Foundation Works For (8) H2SO4 Tanks |
2013 |
Sacred Karbala |
427.000.000 |
145 |
Repairing Cavitations Of AL-Dura Power Station |
2013 |
Baghdad |
950.000.000 |
146 |
Sand Works And Execution Of Fence For AL-Latifiya Gas Factory |
2013 |
Babil |
1.980.924.000 |
147 |
Fire Extinguishing Building In AL-Diwaniyah Gas Plant |
2013 |
Al-Diwaniyah |
233.213.500 |
148 |
Services Building Works For AL-Latifiya Site |
2013 |
Babil |
1.248.816.500 |
149 |
Execution Of Civil & Mechanical Works For AL-Qa'me Gas Factory In Gas Filling Company |
2013 |
AL-Anbar |
746.483.000 |
150 |
Pipes Network For The Residential District In Al-Dora Refinery |
2013 |
Baghdad |
1.680.600.000 |
151 |
Maintenance Of AL-Sarafiya Bridge |
2013 |
Baghdad |
420.000.000 |
152 |
Execution Of The Complete Project For The Infrastructures / University Of Tikrit |
2013 |
Salah AL-Din |
6.698.775.000 |
153 |
Al- Amiriyah Bridge |
2013 |
AL-Anbar |
13.842.645.188 |
154 |
Civil And Electromechanical Works In Al Emarah Gas Plant |
2013 |
Maysan |
4.573.372.750 |
155 |
Execution Of Services Buildings Works In Al-Najaf Gas Plant |
2013 |
Holy Najaf |
1.126.970.200 |
156 |
Earth Works And Fence Execution In Al-Najaf Gas Plant |
2013 |
Holy Najaf |
921.915.000 |
157 |
Constricting Interchange Bridge And Around For Soda Project |
2013 |
Sacred Karbala |
134.000.000 |
158 |
Rehabilitation Of The Area Between The Two Holy Shrines In Sacred Karbalaa |
2013 |
Sacred Karbala |
4.134.798.000 |
159 |
Installation Of Electrical Power Line (2nd Stage) For ZOSS Power Station In AL-Zubair |
2013 |
AL-Basra |
1.103.100.000 |
160 |
Execution Of A Human Rights National Net Bureau |
2014 |
AL-Anbar |
2.064.209.000 |
161 |
Execution Of AL-Hila Electrical Gas Station (2) In Abi Garaq |
2014 |
Babil |
1.952.159.000 |
162 |
Rehabilitation Of Sayedet AL-Najat Church With An Extension Of The Contract No. (2) |
2014 |
Baghdad |
602.354.000 |
163 |
Execution Of Filling Station In AL-Wasiti District |
2014 |
Kirkuk |
1.545.987.000 |
164 |
Misan Housing Complex |
2014 |
Maysan |
30.976.858.715 |
165 |
Execution Of Faculty Of Arts / University Of Sacred Karbalaa |
2014 |
Sacred Karbala |
6.207.862.500 |
166 |
Implementation Of Sewerage And Rain Water Network And Lifting Stations / University Of Sacred Karbalaa |
2014 |
Sacred Karbala |
4.475.394.500 |
167 |
Execution Of Statistics Sections Training Center In AL-Kufa District |
2014 |
Holy Najaf |
2.138.519.000 |
168 |
Filling And Secretion The Land Of Political Prisoners Foundation |
2014 |
AL-Basra |
2.019.800.000 |
169 |
Civil And Electromechanical Works In Aby Ghraib Gas Plant |
2014 |
Baghdad |
2.849.953.500 |
170 |
Rehabilitation Of Beije Gas Plant Shed |
2014 |
Salah AL-Din |
357.525.000 |
171 |
Civil , Mechanical And Electrical Works For Al-Samawa Gas Filling Line |
2014 |
AL-Muthanna |
1.369.267.200 |
172 |
Execution Of Protection Towers No. (10) For Gas Plants |
2014 |
Baghdad ، Babil ، AL-Diwania ، AL-Muthanna ، Maysan |
611.362.000 |
173 |
Planning Section Building |
2014 |
Babil |
1.724.405.460 |
174 |
Execution Of Project And Engineering Test Section Building In Alforat Alawsat Branch |
2014 |
Babil |
440.525.000 |
175 |
Boarding Houses / Bab AL- Muadam (1th stage) |
2014 |
Baghdad |
9.150.858.600 |
176 |
Execution Of National Net For Human Rights Bureau |
2014 |
Maysan |
1.887.848.820 |
177 |
Construction Of Fence And Scrap Area For Southern Branch |
2014 |
AL-Basra |
199.700.000 |
178 |
Rehabilitation And Maintenance Of (3) Cooling Towers In AL-Dora Refinery |
2014 |
Baghdad |
3.210.000.000 |
179 |
Install And Erect AL-Dora Silo |
2014 |
Baghdad |
11.738.350.000 |
180 |
National Net For Human Rights Bureau |
2014 |
Holy Najaf |
2.166.685.620 |
181 |
Construction The Road Of Misan Gas Plant |
2014 |
Maysan |
175.000.000 |
182 |
Construction Of Six School Class Wings (AL-Furat, AL-Hindiya, AL-Nawadim And The Nawaris Kindergarten) |
2014 |
Sacred Karbala |
1.125.493.000 |
183 |
Construction Of Specialized Building For Iraqi Researches And Arabic Codes Project |
2014 |
Baghdad |
3.388.786.500 |
184 |
Design And Implementation Of Printing Machine Building For AL-Sabah Newspaper |
2014 |
Baghdad |
4.661.410.156 |
185 |
Execution And Renew Of Fire Fighting Pipes Network In Al-Dora Refinery / 3nd Stage |
2014 |
Baghdad |
6.850.271.000 |
186 |
Earth Works And Fence Execution For Karbala Gas Plant |
2014 |
Sacred Karbala |
2.893.460.000 |
187 |
National Net For Human Rights Bureau |
2014 |
Al-Diwaniyah |
2.119.560.600 |
188 |
Execution Of Rest House Building For Ministry Of Construction And Housing Staff |
2015 |
Holy Najaf |
2.594.878.550 |
189 |
Construction The Building Of Al-Samawa Police Oil |
2015 |
AL-Muthanna |
323.885.000 |
190 |
Execution Of institution building of oil production distribution in Middle Euphrates. |
2015 |
Babil |
5.073.435.300 |
191 |
Ministry Of Construction & Housing \ Head Office Building |
2015 |
Kirkuk |
8.885.207.810 |
192 |
Establishing Gaseous Generator Piping Plant In AL-Dora Refinery / Third Stage |
2015 |
Baghdad |
587.969.000 |
193 |
Rest House Execution For The Middle Refinery Company / AL-Thaalba |
2015 |
Baghdad |
3.041.971.000 |
194 |
Civil Works For Oil Mixing And Hydrogen Filtration Unit |
2015 |
Baghdad |
1.109.555.000 |
195 |
Execution Of Karbala Civil Laboratory Building |
2015 |
Sacred Karbala |
3.796.762.009 |
196 |
Civil Works For Western Baghdad Power Station Extension |
2015 |
Baghdad |
573.525.000 |
197 |
Execution Of The Boarding House For Oil Training Institute / 2nd Stage |
2015 |
AL-Basra |
6.588.954.000 |
198 |
Earth And Civil Works For The Outer Fence And Guards Building For Transforming Stations In Different Sites |
2015 |
Several Governorates |
10.099.602.500 |
199 |
Construction Of Pumps Foundations In AL-Fao Oil Storage |
2015 |
AL-Basra |
2.450.000.000 |
200 |
Construction A Fence Surrounding The Housing Complex In Gas Filling Company |
2015 |
Baghdad |
796.075.000 |
201 |
Rest House Building |
2015 |
Dhi-Qar |
2.722.759.293 |
202 |
OSBL Pipe Lines For Hydrogen Production Unit |
2016 |
Baghdad |
2.062.885.000 |
203 |
Misan Maternity Hospital |
2016 |
Maysan |
39.783.991.427 |
204 |
Construction Of Two Floors Storage Area In AL-Dora Refinery |
2016 |
Baghdad |
2.486.175.000 |
205 |
Rehabiltation Of Midoil Company Entrance |
2016 |
Baghdad |
342.670.000 |
206 |
Execution Of A Three Stores Building With Extensions For Midland Oil Company Building |
2016 |
Baghdad |
3.815.717.650 |
207 |
Excution Of Steam Pipes Net For Oils Unit No.2 |
2016 |
Baghdad |
426.044.000 |
208 |
Civil And Electromechanical Works For Misan Gas Plant |
2016 |
Maysan |
2.826.994.000 |
209 |
Construction Of Fence And Sub Road For Dyala Gas Warehouse |
2016 |
Diyala |
1.074.565.000 |
210 |
Earth Works And Construction Of Outer Road For Dyala Gas Warehouse |
2016 |
Diyala |
1.680.534.000 |
211 |
Service And Administration Buildings For Circular Storage Tank |
2016 |
Sacred Karbala |
1.594.652.000 |
212 |
Civil, Electrical And Mechanical Works For Gas Filling Pipe Line In Najaf Gas Factory |
2016 |
Holy Najaf |
1.089.355.000 |
213 |
Construction Of Archives Building For The Gas Filling Company In Taji |
2017 |
Baghdad |
359.747.000 |
214 |
Field Works Of Installation And Construction In Samawa |
2017 |
AL-Muthanna |
3.866.552.000 |
215 |
Reconstruction Of Imam Ways Bridges No.(4) And No.(7) |
2017 |
Diyala |
2.322.968.000 |
216 |
Construction Of Concrete Storage Tank In Al-Nasiriya Store |
2017 |
Dhi-Qar |
416.980.000 |
217 |
Execution Of Welding Works For Steam Pipes, Water Pipes And Air Pipes For Polluted Water Unit Within (3000) inch diagonal welded |
2017 |
Baghdad |
60.000.000 |
218 |
Reconstruction Of Al-Dhuluiya Big And Small Bridges And Approaches |
2017 |
Salah AL-Din |
5.633.169.200 |
219 |
Execution Of Welding Works (4000) Inch Diagonal Welded |
2017 |
Baghdad |
90.000.000 |
220 |
Construction Of Research Department Laboratory In Oil Pipelines Company In AL-Doora Refinery |
2017 |
Baghdad |
289.194.000 |
221 |
Carbon Steel Pipe (24) inch From River Intake To Cooling Towers |
2017 |
Baghdad |
164.830.000 |
222 |
Construction Of Financial Department Annix In Gas Filling Company |
2017 |
Baghdad |
739.885.000 |
223 |
Construction Of Cooling Water Pipe For Light Oil Units (54) |
2017 |
Baghdad |
2.738.981.800 |
224 |
Construction Of Cooling Water Pipe For Light Oil Units (36) |
2017 |
Baghdad |
2.464.820.240 |
225 |
Rehabilitation Of Mosul Forth Bridge |
2018 |
Nineveh |
1.044.012.000 |
226 |
Supplying And Installation Of Pontoon At Euphrates River In Heet Region |
2018 |
AL-Anbar |
194.400.000 |
227 |
Development Of AL-Kifil Petrol Public Station |
2018 |
Babil |
2.241.308.500 |
228 |
Paving The Road Of Eight Houses And The Road Parallel To New Buildings In Oil Pipelines Company Headquarters |
2018 |
Baghdad |
414.800.000 |
229 |
Rehabilitation Of Ground floor In Government Counsil Building |
2018 |
Baghdad |
99.980.000 |
230 |
Rehabilitation Of Cylinders Preparing Workshop In AL-Kut Factory |
2018 |
Wasit |
165.000.000 |
231 |
Construction Of Gas Bureau Building In Karbala |
2018 |
Sacred Karbala |
1.305.023.950 |
232 |
Demolition And Rebuilding Of Al-Shora Secondary School |
2018 |
Nineveh |
750.236.000 |
233 |
Supply And Operate Two Elevators For AL-Basra Trade Room |
2018 |
AL-Basra |
121.200.000 |
234 |
Construction Of Brass Store In Gas Filling Company |
2018 |
Baghdad |
122.108.000 |
235 |
Pouring Reinforced Concrete For A Garage Of Cars And Heavy Machines In Gas Filling Company |
2018 |
Baghdad |
167.700.000 |
236 |
Rehabilitation Of Al-Alikhani mosque In Daquk |
2018 |
Kirkuk |
225.000.000 |
237 |
Construction Of Laboratory Building In Holy Najaf Storeroom |
2018 |
Holy Najaf |
116.164.000 |
238 |
Demolition And Rebuilding Of Al-Ashauis School In Samarra |
2018 |
Salah AL-Din |
469.258.000 |
239 |
Construction Of Laboratory Building In AL- Nasiriyah Storeroom |
2018 |
Dhi-Qar |
117.530.000 |
240 |
Rehabilitation Of External Pathways In Council Of State Building |
2018 |
Baghdad |
77.257.500 |
241 |
Extending Cables For Al-Sumood Refinery In Beji |
2018 |
Salah AL-Din |
907.000.000 |
242 |
Demolition And Rebuilding Of Al-Saqlawia Industry Preparatory |
2018 |
AL-Anbar |
1.311.529.150 |
243 |
Construction Of Dhi-Qar Governmental Gas Factory |
2018 |
Dhi-Qar |
880.000.000 |
244 |
Civil Works Of Tikrit University Boarding Houses |
2018 |
Salah AL-Din |
730.462.000 |
245 |
Civil Works For Cooling Towers Of AL-Dora Refinery |
2018 |
Baghdad |
10.382.616.500 |
246 |
Digging a Trench Around The Secure Fence At North Refinery Company Headquarter |
2019 |
Salah AL-Din |
644.000.000 |
247 |
Supply And Connection Of Plastic Pipes With Fittings For Sanitary Pipeline |
2019 |
Baghdad |
244.260.000 |
248 |
Execution Of Digging Fluid Channels In Eastern Baghada Oil Field |
2019 |
Baghdad |
236.346.000 |
249 |
Rehabilitation And Maintainance Of Damaged Buildings Roofs For AL-Sumood Refinery In Beji |
2019 |
Salah AL-Din |
537.550.000 |
250 |
Supply And Extending Cables For Petrol Improvement Unit And Liquid Unit |
2019 |
Salah AL-Din |
1.640.250.000 |
251 |
Building Of Seven Stone Border Stations |
2019 |
AL-Anbar |
887.390.000 |
252 |
Execution Of Boring Piles Works For Three Tanks In Al-Basra Refinery |
2019 |
AL-Basra |
6.113.700.000 |
253 |
Implementation Of Outer Fence , Earth Filling Works And Guards Room For Power Station |
2019 |
Several Governorates |
3.490.077.380 |
254 |
Rehabilitation Of Holy Shrines |
2019 |
Babil |
339.619.500 |
255 |
Building Of Purchase And Contracts Department At Al Sumood Refinery In Beji |
2019 |
Salah AL-Din |
700.655.000 |
256 |
Rehabilitation Of Sheds At AL-Samood Refinery |
2019 |
Salah AL-Din |
1.482.000.000 |
257 |
Construction Of Two-Story's Building For Messan Inspection Branch |
2019 |
Maysan |
245.785.000 |
258 |
Rehabilitation Of (TBI) Bbilding In Al-Sinak |
2019 |
Baghdad |
1.674.420.000 |
259 |
Maintainance Of Clay Crusher LO2 |
2019 |
Holy Najaf |
42.000.000 |
260 |
Demolition And Reconstruction Of AL-Iskandarona School |
2019 |
Kirkuk |
557.435.000 |
261 |
Rehabilitation Of Boarding Houses At AL-Qadisiya Complex In Mosul University |
2019 |
Nineveh |
555.369.000 |
262 |
Demolition And Reconstruction Of Jamal Abdulnaser Secondary School |
2019 |
Salah AL-Din |
528.360.000 |
263 |
Demolition And Reconstruction Of Beji Secondary School |
2019 |
Salah AL-Din |
980.658.750 |
264 |
Construction Of Bank Building In Al Nasiryah |
2019 |
Dhi-Qar |
744.155.000 |
265 |
Construction Of Residential Complex In Al-Shatra |
2019 |
Dhi-Qar |
29.545.874.027 |
266 |
Supply And Extending Electrical Cables For Petrol Improvement And Liquid Gas Units |
2019 |
Salah AL-Din |
513.000.000 |
267 |
National Net For Human Rights Bureau |
2019 |
Sacred Karbala |
2.239.839.750 |
268 |
Curing Under Foundations Of Eductional Open College Building |
2020 |
AL-Basra |
100.000.000 |
269 |
Cleansing Of Paths And Areas From Polluted Soil In Midland Refineries Company |
2020 |
Baghdad |
194.392.475 |
270 |
Paving Service Road Leading To Fuel Loading Site In Al-Shieba With Road And Yard Of Fuel Loding Site In Khor Al-Zubair |
2020 |
AL-Basra |
5.442.195.000 |
271 |
Construction Of Al Darrji Bridge |
2020 |
AL-Muthanna |
5.019.135.000 |
272 |
Kirkuk Water Supply / Second Stage |
2020 |
Kirkuk |
93.897.440.000 |
273 |
Roads And Bridges Building (Baghdad -Yosifya) |
2020 |
Baghdad |
7.385.455.172 |
274 |
Construction Of Concrete Tank In Al-Rasafa Storage |
2020 |
Baghdad |
161.320.000 |
275 |
Supply , Excution And Errection Of Concrete Units (T-Wall) |
2020 |
Baghdad |
372.093.000 |
276 |
Implementation Of Three Shelters In Al Emarah Storage |
2020 |
Maysan |
1.178.100.000 |
277 |
Paving Yard And External Roods At AL-Karkh Store |
2020 |
Baghdad |
3.240.860.000 |
278 |
Demolition And Reconstruction Of Three Police Stations |
2021 |
Kirkuk |
508.113.500 |
279 |
Plumbing And Carpentry Workshop In Salah AL-Din Refinery |
2021 |
Salah AL-Din |
391.115.000 |
280 |
Supply And Excution Of Precast Concrete Piles With Two Test Piles In AL-Dorah Refinery |
2021 |
Baghdad |
1.562.911.200 |
281 |
Design And Execution Of Steel Bridge For Pipes Cross Over In Al-Fatha Zone Between Kirkuk And Salah Al-Din Governorates |
2021 |
Salah AL-Din |
2.375.000.000 |
282 |
Supply , Extension And Filling Of Electirical Cables For (RO) Unit |
2021 |
Salah AL-Din |
324.750.000 |
283 |
Rehabilitation Of Work And Social Affairs Ministry Site |
2021 |
Baghdad |
1.251.968.500 |
284 |
Maintenance And Rehabilitation Of Al-Touz Concrete Bridge |
2021 |
Kirkuk |
2.052.790.000 |
285 |
Construction Of Three Protection Buildings For AKAZ Oil Field |
2021 |
AL-Anbar |
524.850.000 |
286 |
Surfacing Of The Road Leading Towards Pumping Unit In Kirkuk Refinery |
2021 |
Kirkuk |
448.000.250 |
287 |
Dynamic Balance Workshop In Salah AL-Din Refinery |
2021 |
Salah AL-Din |
263.692.000 |
288 |
Rehabilitation Of Tikrit - Alalam Bridge With Its Approaches |
2021 |
Salah AL-Din |
11.519.699.356 |
289 |
Demolition And Reconstruction Of Al-Mutasim district And Rehabilition And Maintaince Of Balad Youth Center |
2021 |
Salah AL-Din |
782.609.500 |
290 |
Construction Of (12) Class School In Al-Nasir Quarter |
2021 |
Kirkuk |
589.644.500 |
291 |
Civil Works For Two Spherical Tanks In Altaji |
2021 |
Baghdad |
1.031.990000 |
292 |
Financial Department Building In Salah AL-Din Refinery |
2021 |
Salah AL-Din |
2.260.249.640 |
293 |
Remaining Works For Al-Hafiz Bridge |
2021 |
Dhi-Qar |
1.008.310.000 |
294 |
Construction Of Archive Building For Contracts Department In Northern Refineries |
2022 |
Salah AL-Din |
424.900.000 |
295 |
Demolition And Reconstruction Of Zummar Secondary School And Rehabilitation Of Abu-Khshab School In Rabiaa |
2022 |
Nineveh |
739.203.600 |
296 |
Building Of Electrial Transformers Reparing Workshop |
2022 |
Nineveh |
904.697.550 |
297 |
Execution Of Workshop For Cars Gas System Addtion In Al-Taji Gas Factory |
2022 |
Baghdad |
869.271.000 |
298 |
Construction Of Youth Center In Tallafar (Contract Extension) |
2022 |
Nineveh |
1.293.785.000 |
299 |
Demoltion And Reconstruction Of Al-Haidarya Fuel Station |
2022 |
Holy Najaf |
5.580.985.000 |
300 |
Construction Of Study Halls In Al-Hawija Technical Institute |
2022 |
Kirkuk |
1.400.697.250 |
301 |
Construction Of The Temporary Iron Bridge As An Alternative To The Al-Khidr Bridge |
2022 |
AL-Muthanna |
1.521.380.000 |
302 |
Maintenance And Rehabilitation Of Cooling Towers In AL-Dorah Refinery |
2023 |
Baghdad |
1.783.360.000 |
303 |
Construction Of General Materials Sheds In Baiji Refinery Stores |
2023 |
Salah AL-Din |
199.950.000 |
304 |
Supplying, Extending And Burying Electrical Cables For The Al-Azmarah Unit In Salah Al-Din Refinery (2) |
2023 |
Salah AL-Din |
1.230.985.000 |
305 |
Construction Of Boarding Houses Builiding In Technical Institute / AL-Hawija |
2023 |
Kirkuk |
1.621.773.250 |
306 |
Iraqi Housing Fund Building |
2023 |
Sacred Karbala |
867.498.670 |
307 |
Construction Of A Fixed Iron Bridge Instead Of The Collapsed Sand Bridge |
2023 |
Maysan |
1.426.700.000 |
308 |
Information Building Of The Ministry Of Construction, Housing, Municipalities And Public Works |
2023 |
Baghdad |
391.955.000 |